Applied Digital Closes $300 Million Bridge Facility to Fund Delta Forge 1 Data Center in Louisiana
Applied Digital Corporation (NASDAQ: APLD) announced Nov. 23 that it has closed a $300 million senior secured bridge facility to fund continued development and construction of Delta Forge 1, its AI Factory data center campus in Louisiana.
The Dallas-based company said the loan was led by a leading global financial institution, which the company did not name. Applied Digital said it expects to seek additional financing to fund completion of construction at the campus.
Applied Digital Bridge Facility Terms
The facility is a $300 million delayed draw term loan with a 364-day maturity. It bears interest at the Secured Overnight Financing Rate (SOFR) plus 300 basis points, making it a floating-rate loan. The loan is secured by the assets of the project and can be prepaid at any time without premium.
Because the loan is structured as a delayed draw facility, Applied Digital will not necessarily receive the full amount at once. Draws are subject to conditions, including:
- Construction milestones
- Regulatory approvals, including state commission approval of electrical rates
- Lender consents
- Certain financial covenants
The short maturity positions the loan as a bridge to longer-term construction or permanent financing rather than a complete funding solution for the campus.
Delta Forge 1 Campus and Hyperscaler Lease
Delta Forge 1 is backed by a long-term lease with a U.S.-based, tier-one investment-grade hyperscaler, according to the company. The campus is a single-tenant hyperscale data center project in Louisiana and remains under construction.
Applied Digital describes itself as a U.S.-based AI data center infrastructure company that designs, develops, owns and operates large-scale, purpose-built campuses serving hyperscale off-takers under long-term contracts. The company says its campuses supply the power, advanced liquid cooling and connectivity needed for artificial intelligence and high-performance computing workloads.
In its fiscal first-quarter filing, the company identified Delta Forge 1 as one of five campuses covered by leases totaling approximately 1.41 gigawatts of critical IT load as of Aug. 31, 2026. The other campuses are Polaris Forge 1, 2 and 3 in North Dakota and Delta Forge 2 in Alabama.
Financial Context for the Data Center Financing
Applied Digital reported fiscal first-quarter 2027 revenue of $341.9 million, up from $80.9 million a year earlier. HPC Hosting revenue was approximately $262.6 million, of which approximately $183.5 million came from tenant fit-out services and approximately $65.8 million from base rental revenue. The company reported a $221 million GAAP net loss attributable to common stockholders for the quarter.
Purchases of property and equipment reached approximately $2.07 billion during the quarter, and debt stood at about $6.4 billion as of the first quarter. Management has cited approximately $36 billion of contracted revenue over initial lease terms across its five campuses, rising to approximately $86 billion if renewal options are included. The company's Polaris Forge 1 campus had 250 MW of live capacity after an additional 75 MW phase was delivered following quarter-end.
Power and Regulatory Considerations in Louisiana
The financing's dependence on state commission approval of electrical rates highlights the role of power availability and pricing in Louisiana data center development. A Louisiana energy report estimated that two major projects in the state, Meta's Hyperion project and Hut 8's West Feliciana facility, could together require up to 7.2 GW, equivalent to the electricity consumption of more than 5 million homes.
In its forward-looking statements, Applied Digital cited several risks, including its ability to satisfy the draw conditions and obtain financing under the facility, complete construction of its campuses as planned, raise additional capital, and maintain relationships with principal customers. The company also noted that if customers do not exercise renewal options under their leases, it will not recognize further revenue from those customers under the respective leases.
Outlook
The bridge loan gives Applied Digital near-term liquidity for Delta Forge 1 while it pursues additional capital. Completion of construction, satisfaction of draw conditions, regulatory approval of electrical rates and arrangement of follow-on financing remain the key steps for the project.