Applied Digital Corporation Reaches Ready for Service at 25 MW Data Hall in Harwood, North Dakota
DALLAS — Applied Digital Corporation (NASDAQ: APLD) announced Nov. 24 that it has completed base-build commissioning for the first 75 MW of the initial 150 MW data center building at Polaris Forge 2 in Harwood, North Dakota. Within that phase, the company said it completed the integrated fit-out of the first 25 MW data hall and achieved Ready for Service on schedule.
The milestone is the first Ready for Service achievement at Applied Digital's second AI Factory campus. It follows the delivery of 250 MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota, the company said.
Applied Digital Commissioning at Polaris Forge 2
Applied Digital said the base-build infrastructure for the full 75 MW phase has been tested and commissioned, allowing the remaining 50 MW to advance through fit-out and customer delivery. Each 150 MW building at the AI Factory campus is commissioned in two 75 MW phases, with three 25 MW data halls tested and commissioned together during each phase, according to the company.
Polaris Forge 2 is a hyperscale data center campus in Harwood, listed at approximately 1.8 million square feet with 280 MW of planned total power.
Lease Terms and Contracted Revenue
The building is fully leased as part of the customer's 200 MW long-term lease at Polaris Forge 2, the company said. The lease contributes to Applied Digital's portfolio of more than $41 billion in contracted base-term lease revenue. The 150 MW lease is with a Tier-One, investment-grade hyperscaler.
The $41 billion figure represents long-term contractual revenue rather than current annual revenue, cash flow or recognized earnings.
Company Comments
"AI infrastructure demand is not theoretical for us. It's backed by long-term customer commitments, and our focus is on delivering against them," said Wes Cummins, Chairman and Chief Executive Officer of Applied Digital. "With our second campus now reaching Ready for Service on schedule, we're demonstrating that our execution model is repeatable. The ability to consistently turn contracted demand into delivered AI capacity is what will define the leaders in this industry, and that's exactly what we're doing at Applied Digital."
Business Model and Recent Activity
Applied Digital describes itself as a U.S.-based AI infrastructure company that designs, develops, owns and operates large-scale, purpose-built data center campuses leased to hyperscale customers under long-term contracts. The company said it supplies power, advanced liquid cooling and connectivity for artificial intelligence and high-performance computing workloads.
The company reported fiscal fourth-quarter and full-year 2026 results for the year ended May 31, 2026. In July 2026, it announced delivery of a second building at Polaris Forge 1, indicating that both North Dakota campuses are being developed as multi-building platforms. Applied Digital shares rose roughly 20% after the company disclosed the hyperscaler lease.
North Dakota's Role in AI Data Center Development
North Dakota has emerged as a location for AI data centers because of relatively low power costs and available grid capacity, according to a 2026 LandGate analysis. Power availability, power density and cooling infrastructure can constrain AI facility growth more than conventional data center real estate considerations.
Polaris Forge 2 is a development asset structured as a power-and-infrastructure lease rather than a property sale. Key underwriting variables for such projects include delivered megawatts and critical IT load, the timing of customer fit-out and revenue commencement, power-supply agreements and grid interconnection, construction costs for liquid cooling and high-density electrical systems, tenant credit and concentration, and the company's access to additional capital.
Outlook
With base-build commissioning of the first 75 MW complete, the next steps at Polaris Forge 2 are fit-out and customer delivery of the remaining 50 MW in the phase. In its forward-looking statements, Applied Digital cited risks including its ability to complete construction of its campuses as planned, to raise additional capital and to obtain financing, as well as its dependence on principal customers and the satisfaction of conditions under its lease agreements, including power supply agreements and regulatory approvals.
Sources
Applied Digital press release, GlobeNewswire, Nov. 24, 2026: https://www.globenewswire.com/news-release/2026/11/24/3409209/0/en/applied-digital-achieves-initial-25-mw-ready-for-service-in-harwood-north-dakota-for-hyperscaler-completes-base-build-commissioning-of-first-75-mw.html