IM Properties and Moto Hospitality File Plans for Toddington Park, a 200,000-Sq.-M. M1 Junction 12 Development

IM Properties and Moto Hospitality have submitted a planning application to Central Bedfordshire Council for Toddington Park, a development at Junction 12 of the M1 near Toddington, Bedfordshire, that could create up to 1,400 jobs, the companies announced on Nov. 25, 2026.
The proposals include around 200,000 sq m, or roughly 2.15 million sq ft, of industrial, logistics and data centre floorspace. The project website describes the scheme as approximately 204,000 sq m. The plans also include an extension to the existing Toddington Southbound Services.
Toddington Park Scheme: Floorspace, HGV Parking and Energy
The Toddington Park proposals combine employment floorspace with motorway services infrastructure. The extension to Toddington Southbound Services would provide a new HGV driver welfare facility and more than 300 additional parking spaces for HGVs and electric HGVs, supported by new solar energy generation and battery storage.
The application is a hybrid submission. It seeks detailed permission for key strategic infrastructure and outline permission to establish the proposed uses of the site. Subject to planning permission, details of future buildings and precise layouts would be considered through subsequent reserved matters applications.
Green Space, Recreational Routes and Biodiversity Measures
More than 20 hectares of green space to the west of the M1 would be opened up for community use. The development would also provide recreational routes on both sides of the motorway and improvements to the River Flit corridor within the site.
These elements form part of a wider package of landscaping and biodiversity measures, including new grassland and woodland. The Icknield Way would be enhanced where it crosses the site, with a new Pegasus crossing intended to help horse riders, cyclists and pedestrians cross more safely.
Consultation and Application Process
The application follows a public consultation held in the spring, when local residents and stakeholders commented on the draft proposals. The plans also reflect advice received through Central Bedfordshire Council's pre-application service. HGV drivers who took part in the consultation suggested facilities they would like to see at Toddington Southbound Services and responded positively to the proposals for additional parking and improved welfare facilities.
IM Properties said feedback from residents, stakeholders and drivers helped refine the application, including the proposals for green space, recreational routes and driver facilities. Further information on how comments shaped the plans is available at imptoddingtonpark.co.uk.
A Social Value Statement submitted with the application sets out how the development could benefit the area beyond the site boundary. IM Properties said the scheme has been shaped by its Sustainable Futures Strategy, which guides its approach to design, sustainability and social value. Moto Hospitality also has an established national programme supporting local communities.
Executive Comments
David Smith, Director for Planning & Communities at IM Properties, said: "Toddington Park's location on the M1 corridor provides an opportunity to meet Central Bedfordshire's growing need for high-quality industrial and logistics floorspace, alongside data centre space to support the nation's digital economy."
Smith added: "The development could create up to 1,400 jobs and attract investment to the area, while providing new green space for local communities and habitats for wildlife. It reflects our commitment to delivering lasting economic, social and environmental benefits through our Sustainable Futures Strategy."
Stuart Rose, Development Manager at Moto, said: "By bringing forward our ambition to improve Toddington Southbound Services alongside IM Properties' vision for Toddington Park, we've developed an integrated proposal that responds to the identified need for additional HGV parking and better driver welfare facilities."
Rose added: "The positive response to the proposed parking has been encouraging, and we'd like to thank everyone who shared their ideas for the new driver facilities and their thoughts on the wider scheme."
Market Context for Logistics and Data Centre Space
The scheme targets two segments of the UK property market: logistics and data centres. Logistics conditions vary by measure. CBRE data put national logistics vacancy at 6.56% in the third quarter of 2026, down 53 basis points from the prior quarter, while Knight Frank put overall vacancy at 8.1% at the end of the third quarter, up from 7.5% at the end of 2025. Knight Frank also forecast average UK rental growth of 2.4% for 2026, down from 4.2% in 2025.
Savills reported a 15% increase in UK logistics take-up in 2025 alongside a 60% contraction in speculative development, noting that data centres and defence and aerospace users are increasing competition for development land. CBRE has said data centres were expected to see record demand and ongoing supply constraints during 2026, driven in part by rising leasing requirements for artificial intelligence workloads.
The hybrid structure of the Toddington Park application means building sizes, layouts and the mix between logistics, industrial and data centre uses would be settled at the reserved matters stage, should permission be granted.
Sources
IM Properties: Plans submitted for Toddington Park development with potential to create up to 1,400 jobs